Quality Control

Plumbing Pressure Test — DWV & Supply

Perform code-required pressure tests before drywall closes the walls.

8 min James O'Brien Reviewed by Maria Delgado, Technical Reviewer, PE v1.1 · reviewed 2026-04-18

The Problem

Leaks discovered after drywall are 10x more expensive to repair. Missed pressure tests are a top cause.

Root Causes

  • Schedule pressure to skip the test step
  • Test held for insufficient time
  • No documented test record

Correct Procedure

  • 1Air- or water-test the DWV system per local code (typically 5 psi / 15 min)
  • 2Water-test supply per code (typically 100 psi / 15 min after 24h stabilization)
  • 3Foreman photographs the gauge at start and end
  • 4File the test record with the inspector before requesting closure

Discussion Questions

Use these to engage the crew and connect the lesson to today's site conditions.

  1. 1What pressure and duration does our code require?
  2. 2How do we document the test for the inspector?
Sources & Review
Author: James O'Brien (25+ yrs) · Reviewed by Maria Delgado, Technical Reviewer, PE.
Published 2024-01-12 · Last technical review 2026-04-18 · Version 1.1 · Languages: EN, ES